The schedule for street repair in Forest Haven is as follows:
Monday all day – Demolition of failed pavement, inspection of soil conditions
Tuesday all day – Install and compact aggregate in open trenches
Wednesday @ 1:00 p.m. – Inspection by Saint Louis County
Thursday a.m. – After passing inspection by Saint Louis County, pour concrete

The full width of the entrance to Forest Haven at Raleigh and Julia Dent will be closed from Wednesday, 11/28, through Sunday, 12/02.  The entrance will be opened on Monday morning, 12/02.  There are two residential driveways that will be blocked by the construction, and we will have the area in front of these driveways open in 2-3 days.  All other fresh poured concrete will be closed for about two weeks.